Strategic ORAT Advice & ORAT Trial Management for Berlin Brandenburg Airport T1

"We thank Mr. Zeiler and ON-BLOCK for their duties and performance, which became part of our success on opening day of the BER"

Roland Böhm, Head of Infrastructure and Systems

 

Project:

ORAT for the Opening of Terminal 1 of Berlin Brandenburg Airport with a capacity of 27 Mio. Passengers per year (Opening in October 2020).

Results:

  • Strategic ORAT advice to the CEO of the BER and the Governmental Supervisory Board 
  • Final Planning & execution of 47 Trial days and training activities
  • Successful short-term replanning and implementation of the adjusted ORAT Trial program due to the COVID-19 pandemic in summer 2020.
  • ON-BLOCK delivered 340 Man-days as Strategic ORAT Advisor directly to FBB and as Senior Trial Project Manager for Fraport AG.

 

Appreciation Letter from the ORAT Head of Berlin Airports: